| Province | Subbasin | % |
|---|---|---|
| Basinwide | - | 100.00% |
| Previous: | Next: |
|---|---|
| 20620 REL 27: 2006-006-00 EXP HABITAT EVALUATION PROJECT |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Full Name | Organization | Write Permission | Contact Role | Work Phone | |
|---|---|---|---|---|---|
| Paul (CBFWF) Ashley | Columbia Basin Fish and Wildlife Foundation | Yes | Contract Manager | lonepinebutte@comcast.net.old | (509) 979-2866 |
| Jann Eckman | Columbia Basin Fish and Wildlife Foundation | Yes | Administrative Contact | jann.eckman@cbfwa.org | (503) 229-0191 |
| Sandra Fife | Bonneville Power Administration | Yes | COR | safife@bpa.gov | (503) 230-3678 |
| Tom (CBFWA) Iverson | Columbia Basin Fish and Wildlife Foundation | Yes | Supervisor | tom.iverson@cbfwa.org | (503) 229-0191 |
| Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
| Donald Rose | Bonneville Power Administration | Yes | Env. Compliance Lead | dlrose@bpa.gov | (503) 230-3796 |
| Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Attach Progress Report in Pisces | A: 132. Submit Progress Report for the period 10/01/2011 through 9/30/2012 | 12/03/2012 | 12/03/2012 | |
| Habitat suitability and habitat units assessed | B: 162. Assess HEP field data | 01/31/2013 | 05/31/2013 | |
| HEP schedule for up-coming field season | C: 174. HEP schedule for FY 2013 field season | 05/03/2013 | 05/03/2013 | |
| Deliverable: Receipt of environmental compliance clearance from BPA | D: 165. Environmental compliance documentation | 05/31/2013 | 05/31/2013 | |
| All FY08/10/11/12 HEP reports submitted to BPA and CBFWA | E: 87. Extension Period: Compile and report HEP results to CBFWA and BPA | 03/31/2014 | 03/31/2014 | |
| All administrative requirements for FY13 contract | F: 119. Perform administrative duties | 03/31/2014 | 03/31/2014 | |
| All planned FY13 HEP surveys complete | H: 157. Conduct FY13 HEP surveys | 09/13/2013 | 09/13/2013 | |
| Habitat suitability and habitat units assessed | I: 162. Extension Period: Assess HEP field data | 01/31/2014 | 09/30/2013 | |
| HEP schedule for 2014 field season | J: 174. Extension Period: HEP schedule for 2014 field season | 03/31/2014 | ||
| Attach Progress Report in Pisces | K: 132. Submit Progress Report for the period 10/01/2012 through 9/30/2013 | 12/20/2013 | 12/31/2013 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Wildlife |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 132 | Submit Progress Report for the period 10/01/2011 through 9/30/2012 | 10/01/2012 | ||||||
| B | 162 | Assess HEP field data | 10/01/2012 | ||||||
| C | 174 | HEP schedule for FY 2013 field season | 10/01/2012 | ||||||
| D | 165 | Environmental compliance documentation | 10/01/2012 | ||||||
| E | 87 | Extension Period: Compile and report HEP results to CBFWA and BPA | 10/01/2012 | ||||||
| F | 119 | Perform administrative duties | 10/01/2012 | ||||||
| G | 185 | Periodic Status Reports for BPA | 10/01/2012 | ||||||
| H | 157 | Conduct FY13 HEP surveys | 10/01/2012 | ||||||
| I | 162 | Extension Period: Assess HEP field data | 10/01/2012 | ||||||
| J | 174 | Extension Period: HEP schedule for 2014 field season | 09/30/2013 | ||||||
| K | 132 | Submit Progress Report for the period 10/01/2012 through 9/30/2013 | 10/01/2012 |